Chhatrapati Sambhajinagar Divisional Commissioner Dilip Gawade reviewed work of the incomplete jackwell at the dam, installation of valves at eight locations as well as placing 2,500 millimetre diameter pipes at 10 places
The city has been getting water just once in 10-12 days. Representational pic
Chhatrapati Sambhajinagar Divisional Commissioner Dilip Gawade has reviewed the work of laying a pipeline from Jayakwadi Dam to Marathwada's largest city, an official said on Sunday.
The project aims to supply 200 million litres of water per day to Chhatrapati Sambhajinagar, he added.
Gawade reviewed work of the incomplete jackwell at the dam, installation of valves at eight locations as well as placing 2,500 millimetre diameter pipes at 10 places, the official said.
There are also issues of lack of enough labourers to speed up the work, he added.
Incidentally, with the city getting water just once in 10-12 days, the Shiv Sena (UBT) has started a month-long protest against the Maharashtra Government.
This story has been sourced from a third party syndicated feed, agencies. Mid-day accepts no responsibility or liability for its dependability, trustworthiness, reliability and data of the text. Mid-day management/mid-day.com reserves the sole right to alter, delete or remove (without notice) the content in its absolute discretion for any reason whatsoever