2025-05-03 06:36 PM IST
Union Railways Minister Ashwini Vaishnaw inspected the upcoming Mumbai bullet train station at Bandra Kurla Complex and said construction is moving at full speed. Currently, work is underway on the deepest level — Basement 3 — which will be used for parking. Vaishnaw said "The work is going on at a rapid speed. The work on the lowest basement-B3 is going on. The work for building the walls of the station has started. The work on the tunnel is also underway. A multi-storeyed building will be built over the station. On B3, cars will be parked, on B2, operational work will be done and on B1 and Ground level, passengers will enter the station. A world-class station is being built here..."